July 24-Aug. 2

Trunk Highway 13 – prior to switching traffic from the north half to the south half

  • Finish concrete work and installing guardrail in various locations along the south half of the roadway.
  • Restoration of some of the areas disturbed by construction.
  • Complete the striping for the traffic switch.

Trunk Highway 13 – after switching traffic from the north half to the south half

  • Begin removing the existing pavement on the north half of the roadway.
  • Begin excavation for the north bridge abutment.
  • Begin excavation for the retaining wall between Trunk Highway 13 and the NE Frontage Road.

County Road 5  south of Trunk Highway 13 

  • Restoration of some of the areas disturbed by construction.


SE Frontage Road

  • Restoration of some of the areas disturbed by construction.
  • Install street lighting.
  • Striping the roadway.

Valley Drive

  • Restoration of some of the areas disturbed by construction.
  • Striping the roadway.


County Road 5 – Trunk Highway 13 to 300 feet south of 126th Street

  • No work is scheduled at this time.


NE Frontage Road

  • No work is scheduled at this time.


Miscellaneous Work

  • Continue relocating private utilities throughout the project.


Schedules are subject to change due to weather and other unforeseen circumstances.