Interchange Construction Updates

Sept. 26-Oct. 4

Trunk Highway 13

  • Finish decking the north half of the bridge.
  • Pour the bridge deck.
  • Grading and placing aggregate on the north half of the roadway.
  • Storm sewer installation along the north half of the roadway.

County Road 5  south of Trunk Highway 13 

  • No work is scheduled at this time.


SE Frontage Road

  • No work is scheduled at this time.

Valley Drive

  • No work is scheduled at this time.


County Road 5 – Trunk Highway 13 to 300 feet south of 126th Street

  • No work is scheduled at this time.


NE Frontage Road

  • No work is scheduled at this time.


Miscellaneous Work

  • Continue relocating private utilities throughout the project.


Schedules are subject to change due to weather and other unforeseen circumstances.

Last updated: 9/26/2014 9:03 AM