Sept. 12-20

Trunk Highway 13

  • Finish constructing the north bridge abutment.
  • Set beams for the north half of the bridge.
  • Construct panels for the retaining wall between Trunk Highway 13 and the NE Frontage Road.
  • Grading and placing aggregate on the north half of the roadway.
  • Storm sewer installation along the north half of the roadway.

County Road 5  south of Trunk Highway 13 

  • Striping the roadway.


SE Frontage Road

  • Striping the roadway.

Valley Drive

  • Striping the roadway.


County Road 5 – Trunk Highway 13 to 300 feet south of 126th Street

  • No work is scheduled at this time.


NE Frontage Road

  • No work is scheduled at this time.


Miscellaneous Work

  • Continue relocating private utilities throughout the project.


Schedules are subject to change due to weather and other unforeseen circumstances.