County Road 5 (Kenrick Avenue) from the Scott County line to County Road 70 (Juniper Way) will be resurfaced. Several inches of the existing pavement will be removed and replaced with new asphalt.
Project timeline
June-September 2025
Get email updates
To receive email updates for this project, email Janan Putz at janan.putz@co.dakota.mn.us. Please include “CP 5-59" in the subject line.
Construction
Oct. 3-11
- Removing top layer of the road on Monday, Oct. 6 and Tuesday, Oct. 7
- Paving the road on Tuesday, Oct. 7 and Wednesday, Oct. 8
Traffic control (barrels and cones) will be off the road at the end of every work day.
Drivers should expect temporary lane closures, flaggers and delays throughout the project. Please allow extra time for travel. Watch for construction signage and be cautious while driving through the construction area.