Dakota County, in cooperation with the City of Eagan, is proposing to reconstruct Cliff Road (County Road 32) from Lexington Avenue (County Road 43) to 0.2 miles east of Dodd Road in Eagan. The project will address safety concerns at the intersection of Cliff Road and Dodd Road, accommodate increasing traffic volumes, create a multi-modal corridor safe for pedestrians and provide improvements that are compatible with the natural and built surroundings.
The project proposes to reconstruct Cliff Road (County Road 32) into a two-lane divided roadway utilizing a raised center median, 8-foot shoulders, curb and gutter and 10-foot shared-use trails on each side of the roadway. The reconstruction will include:
- Turn lanes at public intersections
- A signal modification at Lexington Avenue (County Road 43)
- A roundabout at the intersection of Cliff Road and Dodd Road
- Drainage improvements
- Retaining walls
These recommendations are the result of the
Cliff Road Study that Dakota County, in cooperation with the City of Eagan, completed in March of 2020.
For more information, contact Jake Chapek, project manager, at 952-891-7104 or
jacob.chapek@co.dakota.mn.us.
Virtual open house: Thursday, Oct. 15–Thursday, Nov. 5
Informational Display Boards
Open House Summary
Open House Questions and Answers
In-person event – Oct. 22, 2020
An in-person event was held on Thursday, Oct. 22, 2020 from 4:30-7:30 p.m. at the Eagan Civic Arena (3870 Pilot Knob Road). Project information was displayed for review and staff answered questions.
Provide input
Complete a project feedback form and sign up for project updates
You can also text "“projectinfo cliff road" to 468311.
Preliminary design
On March 17, 2020, the Dakota County Board of Commissioners adopted the results of the Cliff Road Corridor Study and preliminary design. The below geometric layout represents the results of the preliminary design.
Geometric Design
Anticipated project timeline
2020-2021: Final design and right of way acquisition
Fall 2020: Open house #1
Summer 2021: Open house #2