The Burnhaven Library was last renovated in 2010. The Burnhaven Library Renovation project will make necessary updates and reorganize the interior to improve in-demand spaces to better support services and technology. The project will include new furniture, equipment, accessibility improvements, and mechanical and electrical building system upgrades.
Dakota County is currently contracting for the professional design services for this project. The awarded firm will be announced shortly.
Project timeline
- April–May 2025: Concept design
- June 2025: Schematic design, including public review and input
- August 2025: Schematic design approved by Dakota County Board of Commissioners
- January 2026: Design complete
- February 2026: Bidding for construction project
- 2026: Construction work
Timeline is subject to change as the project is developed.
Check back to this webpage to stay up to date on the project. For more information contact us at burnhavenproject@co.dakota.mn.us.