Dakota County is constructing a 2-mile segment of the Veterans Memorial Greenway between Alameda Path and Rich Valley Park in Inver Grove Heights.
The finished greenway segment will consist of a 10-foot-wide paved trail. Other amenities will include:
- Safety and accessibility improvements of the trail crossings at Alameda Path, Alameda Avenue, Akron Avenue and 105th Street
- Grade-separated crossing of Rich Valley Boulevard
- Connections to local trails in Rich Valley Park
- Memorial nodes and seating elements
- Wayfinding and interpretive signage
- Landscaping
- Other features consistent with Dakota County Greenway Standards
Project timeline
April 2024–Spring 2025
Construction
Construction activities are complete for 2024. Final turf establishment, erosion control materials removal, ornamental railing installation and wayfinding sign installations will continue in spring 2025.
Questions?
William Bauer, Construction Project Manager
SEH, Inc.
wbauer@sehinc.com
952-912-2629
Tony Wotzka, Greenways Manager
Dakota County Parks
tony.wotzka@co.dakota.mn.us
952-891-7966