County Project 23-84
Dakota County and the City of Apple Valley are improving Cedar Avenue between 138th Street and County Road 42. The roadway wll be resurfaced and American with Disabilities Act (ADA) improvements will be made.
ADA improvements will include ADA accessible pedestrian ramps, detectable tactile surfaces. These are specialized textured surface that help those with limited or no vision navigate by feel using their feet or a cane.
Project timeline
May 5–July 14
Get email updates
To receive email updates for this project, email Stacy Reilly at stacy.reilly@co.dakota.mn.us. Please include “CP 23-84 Updates" in the subject line.
Access
Construction will occur in four phases:
Phase 1: Northbound outside lane and shoulder closures (about three weeks)
Phase 2: Southbound outside lane and shoulder closures (about three weeks)
Phase 3: Inside lane closures both directions (about 1.5 weeks)
Phase 4: Night milling and paving (three nights total)
Construction schedule
Construction will begin on May 5, with setting up traffic control, saw cutting the roadway and removing the concrete and pavement.