Dakota County and the City of Eagan will be constructing a new traffic signal system and intersection improvements at Pilot Knob (County Road 31) and Corporate Center Drive. The project will better manage issues due to increase of traffic from health offices and businesses and Interstate 494.
Project timeline
Spring–November 2025
Get email updates
To receive email updates for this project, email Janan Putz at janan.putz@co.dakota.mn.us. Please include “CP 31-103 update" in the subject line.
Construction schedule
Aug. 1-9
- No work being done by county contractor.
- Private utilities (Lumen, etc.) will be installing new vaults and relocating their lines outside of the construction area.