County Project 97-144
Dakota County and Hampton and Douglas townships will begin construction on the bridge located on Inga Avenue at Pine Creek. The bridge is south of Highway 50. This project will include tree and shrub clearing, excavation, resurfacing and concrete bridge installation.
Areas disturbed by construction and excavation will be restored for a smoother approach and more functional area.
Project timeline
August 2025-June 2026
Get email updates
To receive email updates for this project, email Janan Putz at janan.putz@co.dakota.mn.us. Please include “CP 97-144 Updates" in the subject line.
Construction
This project is complete. The road is now open to traffic. Final clean up and restoration to areas disrupted by construction will continue. Work will occur off the road.